Huntsham Close, Altrincham – Extension completed
We have now completed all of our works on this single storey extension in Altrincham. The works took just 7 weeks from start to finish which included the demolition of the conservatory and slab that previously stood in its place.
Mossley Road, Saddleworth – Kitchen completed
Our works are complete on this stunning Howdens Burford kitchen. A straight swap, which only took two weeks to complete. This included replacement flooring works, where we have laid Polyflor Colonia Limestone tile to complement the matt cream doors and Oak worktops.
Pennine Road, Hazel Grove – Completed kitchen
All our works are complete on this Howdens Grenwich kitchen in High gloss white. Structural alteration to the dividing wall have opened the kitchen diner area into the family space our clients wanted.
New kitchen project in Saddleworth – Mossley Road
Another new kitchen project in Saddleworth commenced this week. A one in one out project to update the Orange look currently frightening the clients!!! The clients have gone for a Howdens Burford Matt Cream with Oak block laminate work tops.
Huntsham Close, Altrincham – The lids on
Week 5 – As the extensions hipped roof goes on we near the finishing line with the windows and doors due to go in by the end of this week, the project will be weather tight and its on with the internals with no disruption from above!!
The Meadows, Saddleworth – Kitchens going in
Now the alterations are complete and room prepared, the kitchen carcasses soon go in place as the whole project now takes its shape.
Regular blog updates and more on Facebook
If you use Facebook follow this link to our page: https://www.facebook.com/curvebuild Hit the like button and get our regular blog updates and news in your daily feed!!
Huntsham Close, Altrincham – The roof goes on
Despite the poor weather today, our team have battled on to get the roof structure formed as we push to get the extension water tight in week 4 of the project.
The Meadows, Saddleworth – Ready for the kitchen installation
Structural alterations complete, first fix of electrics and plumbing completed, walls plastered and mist coat applied kindly by the client themselves!!! Ready for the jigsaw to take shape!!! Watch this space!!!